Oracle weighs trucked natural gas for Project Jupiter as pipeline slips
Key Summary
Oracle is considering trucking natural gas to its Project Jupiter campus in New Mexico due to delays in the pipeline's construction, which could cost four times more than pipeline gas. The company already relies on trucked gas at other AI data center sites, and the economics of energy-intensive facilities are under pressure. The pipeline's revised in-service target is February 1, 2027, while Oracle's completion goal for Project Jupiter is 2028.
Please see our real time news feed on our Home Page
Pipeline Delays Push Oracle to Truck Natural Gas
Oracle is considering trucking natural gas to its Project Jupiter campus in New Mexico due to delays in the pipeline's construction. The company already relies on trucked gas at other AI data center sites, and the economics of energy-intensive facilities are under pressure.Economics of Trucked Gas
Trucking natural gas is estimated to cost approximately four times more than gas delivered by pipeline. Keeping a power-hungry facility online also requires frequent, large shipments, which adds a logistics headache on top of the price premium.Pipeline Problem
The Green Chile Project pipeline, which was supposed to supply power to Project Jupiter, has been delayed by state permitting problems. The pipeline's in-service date was originally August 15, 2026, but it has now been pushed to February 1, 2027.Force Majeure Notice
Oracle issued a force majeure notice to its developer over power-supply risks in September 2026. The company has publicly maintained that Project Jupiter remains on schedule for its 2028 target completion.Implications for AI Infrastructure
The cost question is the most immediate for Oracle, as paying roughly four times more for fuel puts pressure on the economics of energy-intensive facilities. The longer pipeline delays drag on, the longer that premium lasts.#Oracle#US#AI#NewMexico#Energy#Crypto